NORTHEAST REGION DIRECTOR'S REPORT
Eric Winn, Northeast Regional Director

October 2016

AirportPhone NumberContact PersonConstruction/Info/ Misc
Afton-Grand Lake Regional257-8602Paul & Barbara StatonNo new projects at this time.
Bartlesville661-6297Rick BoswellFBO ramp rehab starting this Fall
Claremore343-0931Eric WinnLED airfield lighting, new concrete hangar access taxiway, and Jet hardstand projects are complete. Planning to construct a new 10 T-Hangar this Fall/Winter
Cookson931-0601Forrest WoodFly-In scheduled November 19th with usually 20+ aircraft and 120+ attendees
Eufala-Fountainhead689-5311Cliff LapachNo new projects at this time.
Eufala Municipal689-2534Patty DanielsNo new projects at this time.
Grove786-6150Lisa JewettWorking on a project to build another 8-bay nested t-hangar. Poker run on Saturday 8th. 
Haskell231-3232Eddie ReynoldsNo new projects at this time.
Henryetta652-8634Don PolsonNo new projects at this time.
Hominy885-2164Dani MullinsRunway crack seal project starting this Fall
Inola-Dobie's697-3263Greg DierksJust had some new hangar space open up, looking for new tenants
Miami541-2290Meagan DoughteryOAC grant for a business jet hardstand, FAA grant for new runway lights, PAPIS, REELS, MIRLS, AWOS, Beacon, and security fence. Project is set to begin by the end of 2017. 1st Annual British Flyers Remembrance Ceremony Fly-In on October 15, 2016. We now have a fb page. Search Miami Regional Airport.
Muskogee684-6343 or 405-496-6580Drew Finishing up work on Rwy 4/22, starting design for main Rwy crack seal project
Okmulgee756-0412Jeremy Porter*see attached
Owasso272-1523 or cell 918-798-2060Roger WiedenJust began rwy resurfacing project, last fly-in had 130+ attend w/ 25 aircraft
Pawhuska287-3040Mike McCartneyNo contact made.
Pryor476-6090Tony SmithWorking on an OAC Jet Hardstand project
Sand Springs246-2605Ken MadisonNo contact made.
S. Grand Lake Regional1-937-623-0039Jim Brown jcbgraham@gmail.comRNAV (GPS) approach is now officially published.  The approach to the south comes down to 541' the north approach comes down to 289'.Concrete has been poured on a new hangar that should be completed in October.  The grass parking area for commuter cars has now been replaced with gravel.
Skiatook396-2797Dan YanceyNo contact made.
Tahlequah Municipal431-4139Greg BushNo contact made.
Tulsa-Richard L. Jones299-5886Steve Mushrush*see attached
Tulsa- Harvey Young298-4044David GuzmanNo projects at this time.
Tulsa International838-5000Jeff Mulder*see attached
Vinita Municipal397-0193Terry WilliamsNew perimeter fence project starting soon, just completed a new 36x50 hangar
Wagoner (Hefner-Easley)485-2554 or 527-7099Larry MorganWorking on getting a land owners permission to clear trees on South end of the airport, also getting new asphalt on the airport entrance road and parking lot
 

Tulsa International Airport:

1.  Rental Car Ready Return Facility:

  • Project will add a third deck to the north half of the terminal building parking garage
  • The rental car companies will occupy the second deck, immediately across the street from their counters on that same level
  • The airport parking system will also gain close to 500 additional covered spaces
  • Construction began July 6, 2015 and is projected to be complete by the end of 2016
  • Contractor is Crossland Construction Company, contract amount = $26,022,578
  • Design Consultant:  Demattei Wong and Associates

2. Upgrade Airfield Access Control System

  • Project will install new wireless infrastructure to support the needs of the new control system
  • Construction began: TBA
  • Contractor is: Generation Electric, Inc. contract amount = $4,011,110
  • Design Consultant: Faith Group LLC.

3. FAA Roof repair

  • Project will replace the roofing on the TUL TRACON building, Generator building and ATCT.
  • Contraction began: July, 2016
  • Contractor is Southeast Tulsa Construction, Inc, Contract amount = $606,276.80
  • Design Consultant: FritzBaily inc

Richard L. Jones, Jr. Airport:

1.  Rehabilitate 1L-19R

  • Project sealed cracks, patched areas of distressed pavement, and provided a 2” asphalt overlay
  • Construction began: TBA
  • Contractor is : APAC Central Inc, contract amount = $2,059,962
  • Design Consultant:  Garver

2. Upgrade Airfield Guidance Signs (Phase III)

  • Project removes and replaces airfield guidance signs, installs conduit and replaces cabling.
  • Construction began: TBA
  • Contractor is: Third Generation Electric, Inc. contract amount = $1,204,719,
  • Design Consultant:  Garver

Okmulgee Regional Airport:

1.  Replace Storm Sewer Lines

  • Project includes the replacement or failing storm sewers.
  • Construction began: October 2016
  • Contractor is: Keystone Construction Inc, contract amount = $102,625
  • Design Consultant:  CEC Infrastructure

Airport Statistics:

TUL:  

  • 12 Months (as of 5/31/16) Enplanements = 1,360,000, down  1% from previous 12 months
  • Calendar Year-to-Date Enplanements (as of 5/31/16) = 892176, down -.3 from 2015

RVS:

  • Calendar Year-to-Date (as of 5/31/16) Operations = 119,100, down  -10.8% from 2015
  • Calendar Year-to-Date (as of 5/31/16) Fuel Flow = 731,610 gallons, down -7.8% from 2015

If you have questions, feel free to let me know.

July 2016

AirportPhone NumberContact PersonConstruction/Info/ Misc
Afton-Grand Lake Regional257-8602Paul & Barbara StatonFireworks show had over 2000 attendies, 1st hangar/home is schedualed this fall
Bartlesville661-6297Rick BoswellNo contact made.
Claremore343-0931Eric WinnLED airfield lighting, new concrete hangar access taxiway, and Jet hardstand projects are within a few weeks of completion, Airshow was a huge success with over 6000 in attendance.
Cookson931-0601Forrest WoodFly-Ins are scheduled for September and October
Eufala-Fountainhead689-5311Cliff LapachNo contact made.
Eufala Municipal689-2534Trish CarryNo new projects at this time.
Grove786-6150Lisa JewettProcess of runway light repair, FBO hangar door repair, T-hangar rehab, Air Race is schedualed for October, design portion for a new T-hangar building.
Haskell231-3232Eddie ReynoldsAdded 2 aircraft for the field, 150 in attendance at the last Fly-In
Henryetta652-8634Don PolsonNo contact made.
Hominy885-2164Dani MullinsTaking bids for tunway resurfacing project.
Inola-Dobie's697-3263Greg DierksNo new projects at this time.
Miami541-2290Meagan DoughteryOpen House July 9th, emergency grant from OAC for runway lighting repair.
Muskogee684-6343 or 405-496-6580Drew Still working on RW 422, hosting a Comimerative Airforce event in September.
Okmulgee756-0412Jeremy PorterNo contact made.
Owasso272-1523 or cell 918-798-2060Roger Wieden*see attached
Pawhuska287-3040Mike McCartney 
Pryor476-6090Tony SmithRunway resurfacing project is complete.
Sand Springs246-2605Ken MadisonODALs project has been completed and commisioned.
S. Grand Lake Regional1-937-623-0039Jim Brown jcbgraham@gmail.comHosted an event with over 1000 attendies, new GPS approaches approved, two new based turbine aircraft, and 3 new hangars available for sale or lease.
Skiatook396-2797Dan YanceyNo projects at this time.
Tahlequah Municipal431-4139Greg BushNo projects at this time.
Tulsa-Richard L. Jones299-5886Steve Mushrush*see attached
Tulsa- Harvey Young346-4220Chip TaylorNo projects at this time.
Tulsa International838-5000Jeff Mulder*see attached
Vinita Municipal256-6468Delbert Bowers (no longer there, no one taking care of the airport at this time) No contact made.
Wagoner (Hefner-Easley)485-2554 or 527-7099Larry MorganNew RW lighting and new beacon complete and clearing trees on south end.

Tulsa International Airport:

1.  Rental Car Ready Return Facility:

  • Project will add a third deck to the north half of the terminal building parking garage
  • The rental car companies will occupy the second deck, immediately across the street from their counters on that same level
  • The airport parking system will also gain close to 500 additional covered spaces
  • Construction began July 6, 2015 and is projected to be complete by the end of 2016
  • Contractor is Crossland Construction Company, contract amount = $26,022,578
  • Design Consultant:  Demattei Wong and Associates

2. Spartan Roof replacement

  • Project will replace 180,000 SF of roofing.
  • Construction began in June 2016 and should be completed in August 2016.
  • Contractor is CPR of Tulsa LLC, Contract amount = $349,434.89.
  • Design Consultant: Crafton Tull & Associates

3. FAA Roof repair

  • Project will replace the roofing on the TUL TRACON building, Generator building and ATCT.
  • Contraction began: TBA
  • Contractor is Southeast Tulsa Construction, Inc, Contract amount = $606,276.80
  • Design Consultant: FritzBaily inc

Richard L. Jones, Jr. Airport:

1.  Rehabilitate 1L-19R

  • Project sealed cracks, patched areas of distressed pavement, and provided a 2” asphalt overlay
  • Construction began: TBA
  • Contractor is : TBA, contract amount = $TBA
  • Design Consultant:  Garver

2. Upgrade Airfield Guidance Signs (Phase III)

  • Project removes and replaces airfield guidance signs, installs conduit and replaces cabling.
  • Construction began: TBA
  • Contractor is : TBA, contract amount = $TBA
  • Design Consultant:  Garver

Okmulgee Regional Airport:

1.  Replace Storm Sewer Lines

  • Project includes the replacement or failing storm sewers.
  • Construction began: TBA
  • Construction began: TBA
  • Contractor is: TBA, contract amount = $TBA
  • Design Consultant:  CEC Infrastructure

Airport Statistics:

TUL:  

  • 12 Months (as of 5/31/16) Enplanements = 526,011, down  4.83% from previous 12 months
  • Calendar Year-to-Date Enplanements (as of 5/31/16) = 125,233, down -.47 from 2015

RVS:

  • Calendar Year-to-Date (as of 5/31/16) Operations = 69,136, up -11.2% from 2015
  • Calendar Year-to-Date (as of 5/31/16) Fuel Flow = 395,800 gallons, down -12.5% from 2015

If you have questions, feel free to let me know.

 

 

 

NORTHEAST REGION DIRECTOR'S REPORT
Lisa Jewett, Northeast Regional Director

January 2016

There are 29 airports in the NE region of Oklahoma. Airports that furnished updated information are as follows:

Afton/Grand Lake Regional (Curtis & Tina Tulleson): No new projects.

Bartlesville (Rick Boswell): No new projects scheduled.

Claremore (Eric Winn): Had a pre-construction meeting last week for the ODL’s Project. Started the design phase for a new parallel taxiway project.

Cookson (Dean Martin): No new projects.

Eufala-Fountainhead: No new construction projects scheduled.

Eufala Municipal (Selena Dornan): Completed apron expansion.

Grove Regiona (Lisa Jewett)l: The Terminal Building Project is 75% complete. The new access road is 75% complete and the Taxiway Bravo/Apron Project started construction last month. New PAPI lights to be installed in 2015.

Haskell: No new projects scheduled.

Henryetta: No new projects scheduled.

Hominy: No new projects. Dani Mullins is new airport manager.

Inola-Dobie’s: No new projects scheduled.

Ketchum (Brent Howard): The runway project is complete.

Miami (Tyler Cline): Advertising for new FBO. No new projects.

Muskogee (Garry Lynn): No new projects.

Nowata:  No new projects scheduled.

Okmulgee (Rick Miller): Airport fencing project is 100% complete.

Owasso/Gundy: No new projects scheduled.

Pawhuska: No new projects scheduled.

Pryor: Scheduled to have runway resurfaced in 2015.

Sand Springs (Ken Madison): In the design phase for Omni Directional Lighting Project.

Skiatook (Shirley Lett): Shirley Lett handling airport issues for the city now.

Tahlequah: No contact made.

Vinita: No contact made.

Wagner (Hefner-Easley): To begin lighting project in 2015.

Tulsa International Airport:

1.  Rental Car Ready Return Facility:

  • Project will add a third deck to the north half of the terminal building parking garage
  • The rental car companies will occupy the second deck, immediately across the street from their counters on that same level
  • The airport parking system will also gain close to 500 additional covered spaces
  • Construction began July 6, 2015 and is projected to be complete by the end of 2016
  • Contractor is Crossland Construction Company, contract amount = $26,022,578
  • Design Consultant:  Demattei Wong and Associates

Richard L. Jones, Jr. Airport:

1.  Rehab Taxiway “A”

  • Project sealed cracks, patched areas of distressed pavement, and provided a 2” asphalt overlay
  • Construction began October 12, 2015 and was complete in mid-November 2015
  • Contractor is APAC Central, contract amount = $1,063,700
  • Design Consultant:  Garver

Okmulgee Regional Airport:

1.  Install PAPI’s Runway 17/35

  • Project installed PAPI’s on both ends of Runway 17/35
  • Construction began September 14, 2015, was completed mid-October
  • Flight check completed December 11, 2015, lights are in use
  • Contractor is Williams Electric, contract amount = $113,342                  
  • Design Consultant:  CEC Infrastructure

Airport Statistics:

TUL:  

  • 12 Months (as of 11/30/15) Enplanements = 1,373,668, up 0.2% from previous 12 months
  • Calendar Year-to-Date Enplanements (as of 11/30/15) = 1,258,422, no change from 2014

RVS:

  • Calendar Year-to-Date (as of 11/30/15) Operations = 172,649, up 33% from 2014
  • Calendar Year-to-Date (as of 11/30/15) Fuel Flow = 1,262,066 gallons, up 12.0% from 2014

October 2015

There are 29 airports in the NE region of Oklahoma. Airports that furnished updated information as follows:

Afton/Grand Lake Regional (Curtis & Tina Tulleson): No new projects.

Bartlesville (Rick Boswell): No contact made.

Claremore (Eric Winn): Pre-construction meeting this week for RW/parallel TW Project. Engineering a concrete TW to be completed by 2015.

Cookson (Dean Martin): No new projects. Very successful fly-in over the weekend.

Eufala-Fountainhead: Cliff Lapach is new airport manager. No new projects scheduled.

Eufala Municipal: Completed close-out for their Apron Extension #1 Project. Beginning Apron Expansion Project # 2 this year.

Grove Regional (Lisa Jewett): Terminal building, TW Bravo and West Apron Projects are completed. Waiting on road and parking lot project to complete. Curbs and gutters are complete. Base rock is finished, waiting on asphalt. We also purchased a new 100LL truck to better service our customers on the west side of the airport.

Haskell: Building a new 60x60 hangar. Has a new Facebook page they are very proud of called Haskell Traffic. They’ve gained many new customers from this.

Henryetta: No new projects planned. Working with Katherine at OAC to get project’s needs.

Hominy: Rec'd grant for runway resurfacing, but they have put the project on hold for now.

Inola-Dobie’s: Just completed construction on an 80 x 80 hangar.

 

JULY  2015

Airport

Phone Number

Contact Person

Construction/Info/ Misc

 

Afton-Grand Lake Regional

257-8602

Paul & Barbara Staton

Building another new box hangar.

 

Bartlesville

661-6297

Rick Boswell

No contact made.

 

Claremore

343-0931

Eric Winn

New ODELs are installed, waiting for final inspection.

 

Cookson

931-0601

Forrest Wood

No new projects planned. They are still cleaning up from flood waters.

 

Eufala-Fountainhead

689-5311

Sue Hughart

I spoke with city hall and they informed me that no one is running the airport at this time. 

 

Eufala Municipal

689-2534

Trish Carry

Trish Carry has taken Selina Dorman's place. They are starting their apron extension project this year.

 

Grove

786-6150

Lisa Jewett

We will have a final walk thru July 31st on the new terminal building. The concrete apron is 95% complete and the Taxiway Bravo project should be completed by July 31st. The runway will be displaced beginning July 27th in order to add the new taxiway connector. Anticipated Grand Opening is Septmeber. We have also purchase a new 100LL truck to better serviceo our customers on the west side of the airport.

 

Haskell

231-3232

Eddie Reynolds

This is a privately owned airport, but they are currently in the process of platting out 40+ acres to sell for private hangar space. They will access a maintenance fee for each.

 

Henryetta

652-8634

Don Polson

No new projects planned.

 

Hominy

885-2164

Dani Mullins

No new projects planned. I spoke to the city manager about attending the OAOA Conference this year.

 

Inola-Dobie's

543-2268

Greg Dierks

Private airport. Changed owners.

 

Ketchum

782-2244

Brett Howard

No new projects at this time.

 

Miami

541-2290

Meagan Doughtery

No new projects scheduled.

 

Muskogee

577-8966

Garry Lynn

No contact made.

 

Okmulgee

756-0412

Jeremy Porter

No contact made.

 

Owasso

272-1523

Roger Wieden

No contact made.

 

Pawhuska

287-3040

Mike McCartney

New city manager has taken over airport operations. He is working with the airport board to compile a list of needs for the airport. No new projects scheduled at this time.

 

Pryor

476-6090

Tony Smith

Waiting to award bid for entire runway resurfacing job.

 

Sand Springs

246-2605

Ken Madison

No new projects schedule. Overlay on taxiway and runway in complete. New taxiway on NW side of airport is also completed.

 

Skiatook

396-2797

Martin Tucker

No contact made.

 

Tahlequah Municipal

431-4139

Greg Bush

No contact made.

 

Tulsa-Richard L. Jones

299-5886

Steve Mushrush

*see attached

 

Tulsa- Harvey Young

346-4220

Chip Taylor

*see attached

 

Tulsa International

838-5000

Jeff Mulder

*see attached

 

Vinita Municipal

256-6468

Delbert Bowers

No contact made.

 

Wagoner (Hefner-Easley)

485-2554

Larry Morgan

No contact made.

 

 

 

 

 

JANUARY, 2015

 

 

There are 28 airports in the NE region of Oklahoma. Airports that furnished updated information are as follows:

 

Afton/Grand Lake Regional: No new projects.

 

Bartlesville: No new projects scheduled.

 

Claremore: Had a pre-construction meeting last week for the ODL’s Project. Started the design phase for a new parallel taxiway project.

 

Cookson: No new projects. 

 

Eufala-Fountainhead: No new construction projects scheduled.

 

Eufala Municipal: Completed apron expansion.

 

Grove Regional: The Terminal Building Project is 75% complete. The new access road is 75% complete and the Taxiway Bravo/Apron Project started construction last month. New PAPI lights to be installed in 2015.

 

Haskell: No new projects scheduled.

 

Henryetta: No new projects scheduled.

 

Hominy: No new projects. Dani Mullins is new airport manager.

 

Inola-Dobie’s: No new projects scheduled.

 

Ketchum: The runway project is complete. 

 

Miami: Advertising for new FBO. No new projects.

 

Muskogee: No new projects. 

 

Nowata:  No new projects scheduled.

 

Okmulgee: Airport fencing project is 100% complete.

 

Owasso/Gundy: No new projects scheduled.

 

Pawhuska: No new projects scheduled.

 

Pryor: Scheduled to have runway resurfaced in 2015.

 

Sand Springs: In the design phase for Omni Directional Lighting Project.

 

Skiatook: Shirley Lett handling airport issues for the city now.

 

Tahlequah: No contact made.

 

Vinita: No contact made.

 

Wagner (Hefner-Easley): To begin lighting project in 2015.

 

Tulsa International Airport:

 

1.  Terminal Building, Concourse “A” Renovation:

  • North half of concourse completed on time
  • American Airlines began operations from there in November 2014
  • South half of concourse is underway, progressing on schedule, and will be complete in June 2015
  • Project is a “mirror image” of renovation work completed on the “B” Concourse in early 2012
  • Construction began in September 2013
  • Project management and design consultant:  Flintco, teamed with Fritz Baily Architects
  • Project budget = $31,000,000

 

2.  Rental Car Ready Return Facility:

  • Project will add a third deck to the north half of the terminal building parking garage
  • The rental car companies will occupy the second deck, immediately across the street from their counters on that same level
  • The airport parking system will also gain close to 500 additional covered spaces
  • Project will be advertised for bids in late January
  • Construction is projected to begin summer 2015 and be complete by mid-2017
  • Design Consultant:  Demattei Wong and Associates
  • Project Budget = $20,000,000

 

 Airport Statistics:

 

TUL:  

  • 12 Months (as of 12/31/14) Enplanements = 1,375,399, up 4.0% from previous 12 months

 

RVS:

  • Calendar Year-to-Date (as of 12/31/14) Operations = 141,888, up 3.1% from 2013
  • Calendar Year-to-Date (as of 11/30/14) Fuel Flow = 1,126,981 gallons, down 8.4% from 2013

 

 

Lisa M. Jewett

Airport Manager

Grove Regional Airport

 

October 2014

 

There are 28 airports in the NE region of Oklahoma. Airports that furnished updated information are as follows:

 

Afton/Grand Lake Regional: No new projects.

 

Bartlesville: No new projects scheduled.

 

Claremore: Three new hangars built on the field, taking bids for new Omni Directional Lighting and started the design phase for a new parallel taxiway project.

 

Cookson: No new projects. Forrest Woods is now managing the airport.

 

Eufala-Fountainhead: No new construction projects scheduled.

 

Eufala Municipal: Working on project to expand their apron.

 

Grove Municipal: T-hangar Project is 100% complete. The Terminal Building Project now has steel going up on new pad and mechanical room in place. The new access road is 50% complete and we had our 1st pre-construction meeting for the Taxiway Bravo/West Apron Project.

 

Haskell: New hangar project is 100%.

 

Henryetta: Recently changed City Managers. Coordinating with him on their airport needs.

 

Hominy: No new projects. Dani Mullins is new airport manager.

 

Inola-Dobie’s: No new projects scheduled.

 

Inola- Buzzard’s: Spoke with Beth Harkcom. She says this is a private landing strip that is open to the public, but she has no interest in OAOA and really doesn’t want me to call her again. Taking this airport off my list.

 

Ketchum: The runway will be closed from the 1st of October to the 1st of November for maintenance and repair. New website: info@southgrandlakeairport.com.  

 

Miami: Final construction meeting scheduled this week for Runway Project. It is 100% complete.

 

Muskogee: Just completed final inspection on Taxiway C. 

 

Nowata:  No new projects scheduled.

 

Okmulgee: Airport fencing project is 90% complete.

 

Owasso/Gundy: No new projects scheduled.

 

Pawhuska: No contact made with airport or city manager.

 

Pryor: Scheduled to have runway resurfaced in 2015.

 

Sand Springs: In the design phase for Omni Directional Lighting Project.

 

Skiatook: No contact made.

 

Tahlequah: No contact made.

 

Tulsa- Richard L. Jones/Tulsa- Harvey Young/Tulsa International: 

Following are items you can report for TUL and RVS at the upcoming OAOA membership meeting. 

 

Tulsa International Airport:

 

1.  Terminal Building, Concourse “A” Renovation:

  • North half of concourse scheduled to complete on time on October 8, 2014
  • American Airlines will occupy the north half and begin operations from there November 5, 2014
  • South half of concourse will begin immediately thereafter and complete in May 2015
  • Project is a “mirror image” of renovation work completed on the “B” Concourse in early 2012
  • Construction began in September 2013
  • Project management and design consultant:  Flintco, teamed with Fritz Baily Architects
  • Project budget = $31,000,000

                        

 Airport Statistics:

 

TUL:  

1.  12 Months (as of 9/30/14) Enplanements = 1,365,067, up 3.9% from previous 12 months

2.  Calendar Year-to-Date Enplanements (as of 9/30/14) = 1,025,172, up 4.3% from 2013

 

RVS:

1.  Calendar Year-to-Date (as of 9/30/14) Operations = 101,499, down 9.4% from 2013

2.  Calendar Year-to-Date (as of 8/31/14) Fuel Flow = 805,909 gallons, down 11.1% from 2013

 

Vinita: No contact made.

 

Wagner (Hefner-Easley): No contact made.

 

 

Lisa M. Jewett

Airport Manager

Grove Municipal Airport

 

 

 

 

July 2014

 

I made contact with 25 airports in the NE region of Oklahoma this quarter. Airports that furnished updated information are as follows:

 

Afton/Grand Lake Regional: Curtis and Tina Tulleson are now running the airport. The airport still has land lease lots available.

 

Bartlesville: Wasn’t able to reach Rick Boswell.

 

Claremore: Completed one hangar and two 50 x 50 hangars are in construction. They are in the design phase of new LED lighting for the parallel taxiway and Omni Directional Lighting, as well.

 

Cookson: Mike Ballard retired and Dean Martin is now the airport manager. A new roof has been put on the FBO and a new sliding security gate was installed.

 

Eufala-Fountainhead: No new construction projects scheduled.

 

Eufala Municipal: Recently completed rehab of Taxiway to include sealing/overlay/striping.

 

Grove Municipal: 8-bay nested t-hangar is complete. Water and sewer line for new terminal project is complete. New access road is 90% complete and footings have been poured for the terminal building. Bids were opened Monday for the new Taxiway Bravo and West Apron Project. 

 

Haskell: Currently platting out 40+ acres to sell for private hangar space. They will access a maintenance fee for each. 

 

Henryetta: No information.

 

Hominy: Tex Bayouth retired. Dani Mullins, acting city manager, is currently overseeing airport operations.

 

Inola-Dobie’s: No new projects scheduled.

 

Inola- Buzzard’s: No new projects scheduled.

 

Ketchum:  Repair to recent runway damage to include new seal/paint should be complete by September 1. Beginning project to add an aqua duct under the runway. Working on land survey for WASP approach.

 

d

Miami: Currently constructing taxiway extension and runway overlay. Will begin terminal building update this year.

 

Muskogee: No new projects scheduled. Traffic and fuel sales are up from this time last year.

 

Nowata: Nothing new to report.

 

Okmulgee: Phase 4 of Fencing Project has started. All hangar doors are being refurbished to include repair and paint.

 

Owasso: Box hangar project is complete and no new projects have been schedule to date.

 

Pawhuska: No new projects.

 

Pryor: Preparing to resurface their runway.

 

Sand Springs: No information.

 

Skiatook: Updating runway lights. Completed runway rehab with the exception of the apron. Cobb Engineering is new airport engineer.

 

Tahlequah: Beginning runway repair in August.


Tulsa International Airport:

1.  Terminal Building, Concourse “A” Renovation:

  • Project will be a “mirror image” of renovation work completed on the “B” Concourse in early 2012
  • Project management and design consultant:  Flintco, teamed with Fritz Baily Architects
  • Project budget = $31,000,000
  • Construction began in September 2013, is on schedule, and will take approximately 18 months to complete
  • Delta Airlines has temporarily moved from Concourse “A” to “B” to open up the north half of Concourse “A” for renovation.

2.  Reconstruction of Runway 18L/36R:

  • Approximately 1,200’ of pavement replaced at both the south and north ends in 2011 and 2012 respectively.
  • Phase 3 reconstructed about 7,000’ of runway pavement (all but the intersection with Runway 8/26) in 2013
  • Phase 4 reconstructed the intersection with Runway 8/26 and some taxiway connections
  • Phase 4 contractor is Interstate Highway Construction, contract amount = $13,311,018
  • Work began January 20, 2014 and all airfield work was complete on June 1, 2014

3.  Improve Runway 18R/36L Safety Area

  • RSA’s at both runway ends to not meet current FAA standards
  • Congressional deadline to bring all RSA’s into compliance is December 31, 2015
  • Following years of planning and evaluation of alternatives, the FAA issued a Runway Safety Area Determination on June 24, 2013
  • RSA Determination supports the installation of Engineered Material Arresting Systems (EMAS) on both ends of the runway, combined with displaced landing thresholds and declared distances to bring the runway into compliance to the maximum extent practicable
  • Planning consultant:  Barnard Dunkelberg
  • Design consultant:  Jacobs
  • Expect construction project to bid in summer 2014 in anticipation of a 2014 AIP grant
  • Construction start projected not later than early 2015

Tulsa - Richard L. Jones, Jr. Airport:

1.  Upgrade Airfield Guidance Signs

·         Project is replacing outdated guidance signs with LED fixtures, installing runway distance remaining signs, relocating airport beacon, installing runway end identifier lights on Runway 1L/19R, and replacing Runway 1R/19L VASI’s with PAPI’s

·         Design consultant :  Garver Engineers

·         Phase 1 work completed in May 2013 included a new electric vault and distribution network across the airfield, and Runway 1R/19L PAPI’s

·         Phase 2 contractor is Libra Electric, contract amount = $1,416,240

·         Phase 2 work completed in June 2014 included new guidance signs for Runway 1L/19R and Taxiway “A”, airport beacon relocation, 1L/19R REILs, and runway distance remaining signs

·         Phase 3 is awaiting AIP grant funding

Airport Statistics:

TUL:  

1.  12 Months (as of 6/30/14) Enplanements = 1,340,966, up 1.85% from previous 12 months

2.  Calendar Year-to-Date Enplanements (as of 6/30/14) = 662,970, up 2.9% from 2013

     note:  9 of the last 10 months have seen increases from the same month one year earlier

RVS:

1.  Calendar Year-to-Date (as of 6/30/14) Operations = 55,811, down 20.0% from 2013

2.  Calendar Year-to-Date (as of 5/31/14) Fuel Flow = 1,312,798 gallons, down 9.3% from 2013

 

Vinita: Preparing for 1,000 foot extension of the south end of runway.

 

Wagner (Hefner-Easley): Will start new taxiway and runway lighting project this year.

 

 

 

 

Lisa M. Jewett

Airport Manager

Grove Municipal Airport

 

 

 

 

 

 

 

********************************************************************************************************************************************************************

 

OAOA Report for NE Oklahoma

April 2014

 

I made contact with 27 airports in the NE region of Oklahoma this quarter. Airports that furnished updated information are as follows:

 

  1. Afton/Grand Lake Regional: No new info available.

 

  1. Bartlesville: Project to remove all asphalt and replace with concrete is 95% complete.

 

  1. Claremore: Completed taxiway extension. Working on design for parallel taxiway and Omni directional lighting. Noted he still hasn’t received notice for OAOA dues.

 

  1. Cookson: No contact made.

 

  1. Eufala-Fountainhead: No new construction projects scheduled.

 

  1. Eufala Municipal: Recently completed rehab of Taxiway to include sealing/overlay/striping. Currently working with architect/contractor to build a pilot’s lounge addition.

 

  1. Grove Municipal: T-hangar Project is 100% complete. Construction for Terminal Building Project is anticipated to begin at the end of May. Taxiway Bravo/West Apron Project will begin shortly after that. Water and sewer line project for west side development is 50% complete and new access road is under construction. We have three new private hangars completed and one under construction.  

 

  1. Haskell: Five bay t-hangar is under construction. 

 

  1. Henryetta:  New city manager is currently working to compose a plan for the airport. 

 

  1. Hominy: Nothing new to report.

 

  1. Inola-Dobie’s: No new projects scheduled.

 

  1. Inola- Buzzard’s: No new projects scheduled.

 

  1. Ketchum: New aviation service hangar complete.  WASP approach is complete. 

 

  1. Miami: Recently awarded APAC contract on taxiway extension and runway overlay.

 

  1. Muskogee: New private hangar (7,500 square feet) completed. 

 

  1. Nowata: Nothing new to report.

 

  1. Okmulgee: Nothing new to report.

 

  1. Owasso: Construction of two box hangars complete.

 

  1. Pawhuska: No new projects scheduled.

 

  1. Pryor: Have a runway resurfacing project scheduled for FY 2014.

 

  1. Sand Springs: Runway overlay and sealcoat project complete. No new projects scheduled.

 

  1. Skiatook: Completed RW LED lights and two PAPIs.New fuel sysem near completion.

 

  1. Tahlequah: Constructing a new turnaround at the end of their runway plus a new lighted windsock.

 

  1. Tulsa- Richard L. Jones/ Tulsa-Harvey Young/Tulsa International: 

 

            Reorganization Effort

1.  As of January 1, 2014, the airports have re-structured their operating lease with the City of Tulsa, and are now operating in a more autonomous manner

2.  The Tulsa Airports Improvement Trust (TAIT) has developed the capability to provide many of its own services rather than utilize various city functions – the change is expected to result in at least $500,000 annual savings in operating costs for the airports

3.  Major items that TAIT now provides for itself include Information Technology, Financial, and Human Resources services

4.  The change includes airport employees now being employed by TAIT rather than the City of Tulsa

 

Tulsa International Airport:

 

1.  Terminal Building, Concourse “A” Renovation:

  • Project will be a “mirror image” of renovation work completed on the “B” Concourse in early 2012
  • Project management and design consultant:  Flintco, teamed with Fritz Baily Architects
  • Project budget = $31,000,000
  • Construction began in September 2013 and will take approximately 18 months to complete
  • Delta Airlines has temporarily moved from Concourse “A” to “B” to open up the north half of Concourse “A” for renovation.

 

2.  Reconstruction of Runway 18L/36R:

  • Approximately 1,200’ of pavement replaced at both the south and north ends in 2011 and 2012 respectively.
  • Phase 3 reconstructed about 7,000’ of runway pavement (all but the intersection with Runway 8/26) in 2013
  • Phase 4 is reconstructing the intersection with Runway 8/26 and some taxiway connections
  • Contract awarded to Interstate Highway Construction for the fourth phase of reconstruction, contract amount = $13,311,018
  • Work began January 20, 2014 and is projected to be fully complete before the end of June 2014

 

3.  Upgrade In-Line Outbound Baggage Conveyor System

  • Project upgraded the existing baggage conveyor system that takes checked baggage through screening
  • Approximately 90% of the funding provided by the Transportation Security Administration
  • Contract awarded to Diversified Conveyors, contract amount = $4,508,752
  • Work on the conveyors began in October 2012 and was completed in December 2013

 

4.  Improve Runway 18R/36L Safety Area

  • RSA’s at both runway ends to not meet current FAA standards
  • Congressional deadline to bring all RSA’s into compliance is December 31, 2015
  • Following years of planning and evaluation of alternatives, the FAA issued a Runway Safety Area Determination on June 24, 2013
  • RSA Determination supports the installation of Engineered Material Arresting Systems (EMAS) on both ends of the runway, combined with displaced landing thresholds and declared distances to bring the runway into compliance to the maximum extent practicable
  • Planning consultant:  Barnard Dunkelberg
  • Design consultant:  Jacobs
  • Expect construction project to bid in summer 2014 in anticipation of a 2014 AIP grant
  • Construction start projected not later than early 2015

 

 

Richard L. Jones, Jr. Airport:

 

1.  Upgrade Airfield Guidance Signs

  • Project is replacing outdated guidance signs with LED fixtures, installing runway distance remaining signs, relocating airport beacon, installing runway end identifier lights on Runway 1L/19R, and replacing Runway 1R/19L VASI’s with PAPI’s
  • Design consultant :  Garver Engineers

 

 

  1. Vinita: No other projects scheduled.

 

  1. Wagner (Hefner-Easley): Working on new taxiway and runway lighting project. 

 

 

Lisa M. Jewett

Airport Manager

Grove Municipal Airport

 

*********************************************************************************************************************************************************************************

 

OAOA Report for NE Oklahoma

January 2014 

I made contact with 26 airports in the NE region of Oklahoma this quarter. Airports that furnished updated information are as follows:

  1. Afton/Grand Lake Regional: No new info available.
  2. Bartlesville: Starting a project to remove all asphalt and replace with concrete.
  3. Claremore: Completed Grant Application and now preparing infrastructure for new taxiway extension. Rec’d grant from OAC for all new approach lighting to replace currents REIL lights.
  4. Cookson: No contact made.
  5. Eufala-Fountainhead: No new construction projects scheduled.
  6. Eufala Municipal: Recently completed rehab of Taxiway to include sealing/overlay/striping. Currently working with architect/contractor to build a pilot’s lounge addition.
  7. Grove Municipal: T-hangar Project is 90% complete. Bids for the new Terminal Building Project have been opened and contractor selected. Taxiway Bravo/West Apron Project will begin shortly after that. Water and sewer line project for west side development started this week as well as new access road construction. We have two new private hangars completed, one under construction and one that started dirt work this week.
  8. Haskell: Currently platting out 40+ acres to sell for private hangar space.
  9. Henryetta: Nothing new to report.
  10. Hominy: Nothing new to report.
  11. Inola-Dobie’s: No new projects scheduled
  12. Inola- Buzzard’s: No new projects scheduled.
  13. Ketchum: New aviation service hangar under construction.  Working on land survey for WASP approach.
  14. Miami: Recently awarded APAC contract on taxiway extension and runway overlay.
  15. Muskogee: Taxiway Project completed. Nothing new to report.
  16. Nowata: This airport is currently being run by the local town doctor. He is also an FAA Certified physician. He is showing an interest in OAOA and would like to talk with the OAC concerning airport improvements but is under the impression they can’t get any help because their runway is not 3,000 feet. He would like Dale Williams to contact him either by phone or email. Dr. David Caughell @ 918-331-6208 or doc@nowatafamilymedicine.com.
  17. Okmulgee: Completed Phase 2 of the Fencing Project.
  18. Owasso: Construction of two box hangars complete.
  19. Pawhuska: No new projects scheduled.
  20. Pryor: Have a runway resurfacing project scheduled for FY 2014.
  21. Sand Springs: Runway overlay and sealcoat project complete. No new projects scheduled.
  22. Skiatook: Martin Tucker is no longer there. Dan Yancy will be handling all airport issues.
  23. Tahlequah: Constructing a new turnaround at the end of their runway plus a new lighted windsock.
  24. Tulsa- Richard L. Jones: See attached report.

    Upgrade Airfield Guidance Signs

    ·         Project will replace outdated guidance signs with LED fixtures, install runway distance remaining signs, relocate airport beacon, install runway end identifier lights on Runway 1L/19R, and replace Runway 1R/19L VASI’s with PAPI’s

    ·         Design consultant :  Garver Engineers

    ·         Phase 1 work completed in May 2013 included a new electric vault and distribution network across the airfield, and Runway 1R/19L PAPI’s

    ·         Contract awarded for phase 2 to Libra Electric, contract amount = $1,416,240

    ·         Phase 2 work will begin construction January 21, 2014 – includes new guidance signs for Runway 1L/19R and Taxiway “A”, airport beacon relocation, 1L/19R REILs, and runway distance remaining signs 

  25. Tulsa- Harvey Young: See attached report.
  26. Tulsa International: 

    1.  Terminal Building, Concourse “A” Renovation:

         ·         Project will be a “mirror image” of renovation work completed on the “B” Concourse in early 2012

         ·         Project management and design consultant:  Flintco, teamed with Fritz Baily Architects

         ·         Project budget = $31,000,000

         ·         Construction began in September 2013 and will take approximately 18 months to complete

         ·         Delta Airlines has temporarily moved from Concourse “A” to “B” to open up the north half of Concourse “A” for renovation.

     

    2.  Reconstruction of Runway 18L/36R:

         ·         Approximately 1,200’ of pavement replaced at both the south and north ends in 2011 and 2012 respectively.

         ·         Phase 3 reconstructed about 7,000’ of runway pavement (all but the intersection with Runway 8/26) in 2013

         ·         Phase 4 will reconstruct the intersection with Runway 8/26 and some taxiway connections

         ·         Contract awarded to Interstate Highway Construction for the fourth phase of reconstruction, contract amount = $13,311,018

         ·         Work will begin January 20, 2014 and is projected to be fully complete at the end of June 2014

         ·         A project is in progress for pavement work on the west side runway and taxiway system in anticipation of increased use of the west portion of the airfield by air carrier traffic during reconstruction of the intersection of runways 18L/36R and 8/26 – estimated completion the week of January 13, 2014

     

    3.  Upgrade In-Line Outbound Baggage Conveyor System

         ·         Project upgraded the existing baggage conveyor system that takes checked baggage through screening

         ·         Approximately 90% of the funding provided by the Transportation Security Administration

         ·         Contract awarded to Diversified Conveyors, contract amount = $4,508,752

         ·         Work on the conveyors began in October 2012 and was completed in December 2013

     

    4.  Improve Runway 18R/36L Safety Area

         ·         RSA’s at both runway ends to not meet current FAA standards

         ·         Congressional deadline to bring all RSA’s into compliance is December 31, 2015

         ·         Following years of planning and evaluation of alternatives, the FAA issued a Runway Safety Area Determination on June 24, 2013

         ·         RSA Determination supports the installation of Engineered Material Arresting Systems (EMAS) on both ends of the runway, combined with displaced landing thresholds and declared distances to bring the runway into compliance to the maximum extent practicable

         ·         Planning consultant:  Barnard Dunkelberg

         ·         Design consultant:  Jacobs

         ·         Expect construction project to bid in summer 2014 in anticipation of a 2014 AIP grant

         ·         Construction start projected in the second half of calendar year 2014

    Airport Statistics:

    1.    Calendar year-to-date Passenger Enplanements at TUL (as of 11/30/13) = 1,210,259, down 1.1% from 2012

    2.    Calendar year-to-date Operations at RVS (as of 11/30/13) = 129,370, down 20.3% from 2012

    3.    Calendar year-to-date Fuel Flow at RVS (as of 10/31/13) = 1,132,821 gallons, down 3.3% from 2012
     

  27. Vinita: No other projects scheduled.
  28. Wagner (Hefner-Easley): Working on new taxiway and runway lighting project. No other project scheduled.

 

Lisa M. Jewett

Airport Manager

Grove Municipal Airport